Quarterly Progress Update March 2021April 15, 2021|By admin Quarterly Progress Update March 2021 Structure Block A completed up to level 42. Level 43 swimming pool and road infra works are in progress. Overall Tower Block A structure works view from level 28 - 42. Overall front view for structure works Block A & B. Structure works Block A & B up to level 43 facilities area. Sky bridge connection are in progress. Podium car park level P1 to level P7 completed with first scheme color. Level 8 facilities floor structure completed for softscape and hardscape works. PrevNext